Brisbane Stadium powers ahead with 100 days of early works

Victoria Park is being reshaped as preparations for the foundations of Brisbane Stadium gather pace.

Early works contractor BMD have moved more than 200,000 cubic metres of earth and rock during the first 100 days for the new Brisbane Stadium, marking another major step towards construction. That’s enough material to fill around 80 Olympic swimming pools.

More than 60 people are working onsite each day as crews reshape the hilly terrain to create a level, compacted platform for stadium construction.

Working with the natural slope of Victoria Park, BMD is using a cut-and-fill approach with more than 12 metres being cut from some parts of the site, while up to seven metres of fill is being added in other areas.

Early works will continue into 2027, while design and procurement progress ahead of the next phase of construction.

The 63,000-capacity Brisbane Stadium will host the opening and closing ceremonies and athletics during the 2032 Games, before becoming Queensland’s main stadium in legacy mode, providing a new home for major AFL and cricket fixtures as well as international sport and entertainment.

The stadium is part of a bigger transformation underway at Victoria Park.

Public consultation on the Victoria Park Precinct Draft Legacy Plan ran from 3 August to 27 September 2026, providing people with the opportunity to have their say on the draft legacy plan.

More than 42,000 people visited the precinct webpage during consultation, with feedback calling for better connections, green space and a precinct people can enjoy every day. Feedback will help shape the final legacy plan, to be released in 2027.